GASMIG GASODUCT | BRUMADINHO NOVA LIMA (MG)

In 2007, we carried out the Installation of the CMRP SKID, carried out the complete installation of the set of valves at the Brumadinho Gas Receiving Station.

ABOUT THE WORK

Executed City-Gate with cathodic protection, odor dispersion system, lighting and lightning protection system and special crossing works, and crossings by Non-Destructive Method (MND) in a stream (100.00 m), in Lagoa das Codornas (120, 00 m) and intersections of BR-040 (80m), BR 356 (160.00 m).

  • Diameter: 10″
  • Length: 33,278 meters
  • Material: API 5L Grade B Steel
  • Non-Destructive Method (NDM)

CLIENT: GASMIG
SEGMENT
: GAS PIPELINE
LOCATION
: BRUMADINHO NOVA LIMA/MG

  • Clients:
    GASMIG
  • Category:
    Oil, Gas and Ethanol
  • Date: